24.06.2004
Provisory steel beam test assembly
A steel structure of 16 metre long and weighing 3,7 tons has been assembled on June 24th at CMB factory to check the compliance with the design done by Hecla and Linuhönnun. It is expected to be erected in September on a tower type A4B3 of the double circuit 400 kV line Granzay-Les Jumeaux in western French region.
This device has been designed to keep alive one circuit when works are carried out.
|